Milwaukee Significantly Behind in Project to Replace 1,100 Lead Pipes by End of Year

August 15, 2020

By Matt Martinez
Milwaukee Neighborhood News Service

This story was originally published by Milwaukee Neighborhood News Service, where you can find other stories reporting on fifteen city neighborhoods in Milwaukee. Visit milwaukeenns.org.

The lead service replacement project began four years ago after the city found an unsafe number of lead laterals, or service lines. (File photo by Jabril Faraj)

The city is significantly behind in its goal to replace 1,100 lead pipes by the end of the year, exacerbated in part by the ongoing pandemic, Milwaukee officials say.

As of Aug. 10, only 333 lines have been replaced, according to data on the Milwaukee Water Works website.

The lead service replacement project began four years ago after officials found an unsafe number of lead laterals, or service lines, connecting water mains to houses and businesses.

The lead from these lines leaches into tap water and can have unhealthy effects on those who drink it, especially developing children.

The project replaces lead pipes with copper ones.

During a July 15 meeting of the Milwaukee Common Council’s Public Works Committee, Ald. Milele Coggs said the rate of replacement is too slow. Coggs called for more options for residents.

“My goal is to get to a point where you don’t have to wait until stuff is disrupted to be able to replace your lead laterals,” Coggs said.

Milwaukee Water Works Superintendent Karen Dettmer said her department did not feel comfortable sending workers out during the early part of the pandemic, because so much about the virus was unknown at the time. Officials, she said, did not want to put workers or residents at risk.

The process of replacing the lines requires multiple people entering a home or business.

Because of the risk of exposure, Dettmer said, some residents did not want workers entering their homes.

While the pandemic did slow the program, Dettmer said workers have made significant progress at child care centers that have been closed during the shutdown.

“It’s not a simple answer as far as moving forward with lead service line replacement,” Dettmer said. “If we had an infinite amount of funding, it would be a much simpler answer.”

Dettmer said the price of replacing lead service lines has increased, and the city’s budget will face constraints in the future.

Dettmer is proposing a new plan that would evenly distribute revenue from water rates to help fund service line replacements. The water main replacement project will affect 300 properties with lead service lines.

With 70,000 lead service lines in the city, it would take roughly 70 years for the program to reach its goal.

For Robert Penner, a member of Get The Lead Out coalition, that’s too long. The coalition is made up of residents and community organizations.

Penner cited Lansing, Michigan, as the “gold standard” for lead replacement. He acknowledged that it is a smaller city than Milwaukee. Lansing had to replace 12,150 pipes as opposed to Milwaukee’s 70,000.

“We see that as absolutely unacceptable,” Penner said. “We’ve seen in other cities that this type of project can be accomplished in a few years.”

Share:

  • Click to share on Facebook (Opens in new window) Facebook
  • Tweet
  • Click to email a link to a friend (Opens in new window) Email
  • Click to print (Opens in new window) Print

Popular Interests In This Article: Karen Dettmer, Lead Pipes, Lead Service Lines, Matt Martinez, Robert Penner

Read More - Related Articles

  • Lead Hazards are Everywhere in Milwaukee. Here’s What You Can Do to Mitigate Them.
  • President Biden Visits Milwaukee
  • Hiring Workers is Vital to Speeding up Lead-Pipe Replacement in Milwaukee
  • Lead Lateral Replacement Timeline Doesn’t Add Up
  • Milwaukee Makes Plans to Replace Lead Service Lines. Is There Money to pay for it?
Become Our Fan On Facebook
Find Us On Facebook


Follow Us On X
Follow Us On X

Editorials

Lakeshia Myers
Michelle Bryant
Dr. Kweku Akyirefi Amoasi formerly known as Dr. Ramel Smith

Journalists

Karen Stokes

Topics

Health Care & Wellness
Climate Change
Upcoming Events
Obituaries
Milwaukee NAACP

Politicians

David Crowley
Cavalier Johnson
Marcelia Nicholson
Governor Tony Evers
President Joe Biden
Vice President Kamala Harris
Former President Barack Obama
Gwen Moore
Milele A. Coggs
Spencer Coggs

Classifieds

Job Openings
Bid Requests
Req Proposals
Req Quotations
Apts For Rent

Contact Us

Milwaukee Courier
2003 W. Capitol Dr.
Milwaukee, WI 53206
Ph: 414.449.4860
Fax: 414.906.5383

Copyright © 2025 · Courier Communications | View Privacy Policy | Site built and maintained by Farrell Marketing Technology LLC
We use third-party advertising companies to serve ads when you visit our website. These companies may use information (not including your name, address, email address, or telephone number) about your visits to this and other websites in order to provide advertisements about goods and services of interest to you. If you would like more information about this practice and to know your choices about not having this information used by these companies, click here.